1. Call to Order/Roll Call
Mr. Baruzzi called the
meeting to order at 5:05 p.m.
2. Meeting Minutes
The minutes of August 20, 2008 were moved, seconded and approved unanimously.
3.
No one came forward.
4.
Fuss
& O’Neil re: MMS Fossil Fuel Project
Mr. Callahan reported that the bid walk-through was held with a good turnout of qualified contractors. Bids are due on September 24th with the plan to have them reviewed and returned within two weeks of the opening.
5. Architect’s Report
Mr. Lawrence reported he has renumbered the options per the Committee’s request and explained the changes in the handout.
Mr. Baruzzi clarified some of the changes in the Lawrence Associates handout per the School Administrator’s meeting held the day before.
A discussion followed on the Informational Meeting
scheduled for September 17th at the
6. Construction Manager Services
Mr. Lawrence reported that the numbers are correct as they are and the project should go to referendum by spring.
7. Other
The next School Building Committee meeting will be
held October 8, 2008 in Conference Room B at 5:00, with the MMS Fuel Conversion
being held on the same date and location.
8. Adjournment
Mr. Baruzzi
adjourned the meeting at 5:50 p.m.
Respectfully submitted,
Linda Patenaude
Capital Projects and Personnel Assistant