TOWN OF
SCHOOL
BUILDING COMMITTEE
Present: Mary
Feathers, Chair, Gordon Schimmel, Anne Willenborg (5:40), Elizabeth Paterson
Absent: Cherie Trahan, Anne Rash, Mark Boyer,
Eric Ohlund
Staff: William
Hammon, Jeff Smith, Jaime Russell, Fred Baruzzi, Matt Hart, Candace Morrell,
Norma Fisher-Doiron, Jim Palmer (5:30)
Guest: Rick
Lawrence, Rick Lawrence Associates, Tom DiMauro, Newfield Construction,
1.
Call to
Order/Roll Call
Ms. Paterson called the
meeting to order at 5:04 p.m.
2.
Meeting
Minutes
The minutes of March 12, 2008 were moved, seconded and approved unanimously.
3.
No one came forward.
4.
Fuss
& O’Neil re: MMS Fossil Fuel Project
Update from Mr. Hart regarding the 4:00 MMS Fossil Fuel Project. Mr. Hart reported that Fuss & O’Neill is focusing on the State approval process. A Plans Approval Test is being completed on May 12th. This will be final. Mr. Smith reported that if approved it could go out to bid within the next couple of weeks after approval.
5.
Architect’s
Report
Mr. Lawrence reported Newfield Construction has been concentrating on the cost estimates. Mr. Lawrence presented preliminary numbers from Newfield Construction using “Rule of Thumb” numbers based on current projects and adding escalation.
Mr. Lawrence explained the handout in detail.
6.
Construction
Manager Services
Mr. DiMauro explained in detail how he came up with
the breakdown and options for the numbers.
7.
Other
The
next School Building Committee meeting will be on May 14, 2008 at 5:00
p.m. The MMS Fuel Conversion Project
will be on May 14, 2008 at 4:00 p.m.
8.
Adjournment
Mr. Hart adjourned the meeting at 5:57 p.m.
Respectfully submitted,
Linda Patenaude
Capital Projects and Personnel Assistant